40 percent works on Karnaphuli tunnel nearing completion

  • Print
Chattogram Bureau :
The works of preliminary phase have been  near about completion stage. Project  Director of Karnaphuli tunnel project Harunur Rashid Chowdhury told the media persons that 40 percent of the total project works have  been completed in the meantime.
He said at Anowara site of the tunnel, power line and sub-station construction is progressing fast  and  road construction works in Patenga site is quickly advancing. Project director also said the construction of working shaft, cut under cover already completed. He said out of total 382 acres of land so acquisitioned for the project and the remaining under process.
 Following the formal inauguration of construction works by the Prime Minister on February 24 last, the speed of works  accelerated further . Project Director further said the total cost estimated Tk.9,900 crores for 3.32 kilometers long tunnel under Karnaphuli river in Chattogram.
 Chinese Exim Bank will provide Tk.5,900 crores with the  remaining will be borne by Bangladesh govt . The total project work is expected to be completed by 2022 , sources said.

More News For this Category

CDA to handover responsibilities of flyovers to CCC

CDA to handover responsibilities of flyovers to CCC

Chattogram Bureau :The implementing organization of the flyovers in port city - Chattogram Development authority  has taken initiatives to handover the responsibilities of  repairs, renovation s and maintenance of

Information Minister attends  TV Journalists' Association installation ceremony

Information Minister attends TV Journalists' Association installation ceremony

Chattogram Bureau :Information Minister Dr Hasan Mahmud said that there were many problems in the media. The present government is working to resolve the problem. The government is doing

Road communication with Bandarban restored

BSS, Bandarban :Road communication of Bandarban hill district with the rest of the country has been restored  yesterday after eight days of disruption due to flood.Flood situation in the

A view of traffic congestions in Chattogram Port  Road yesterday.

A view of traffic congestions in Chattogram Port Road yesterday.

.

 Percentage of pass lower than previous year

Percentage of pass lower than previous year

UNB, Chattogram : A  total of 62.19 percent students passed the HSC and equivalent examinations under Chattogram Education Board (CEB) which is 0.54 percent lower than that of the previous

Long gridlock on Port Road, claimed working groups

Chattogram Bureau :Traffic congestions in the port connecting road and airport road from  Customs circle  is a regular phenomenon  of the port city, which creates anxiety among the garments

1320 MW power plant at Mirsharai Economic Zone  soon

1320 MW power plant at Mirsharai Economic Zone soon

Chattogram Bureau :A Chinese origin industrial concern named Union Resources Engineering Co Ltd will build a 1320 Megawatt power plant at Mirsharai Economic Zone under Bangabandhu Sheikh Mujib Shilpanagar 

Human Chain held at CU

CU Correspondent :Students of Chittagong University  formed a human chain supporting Prof ABM Faroque, who recently conducted two tests on milk samples of various companies.Students of different faculties and

Indu Nandan Dutt, Member of  Standing Committee of JASAD speaking  at a human chain demanding implementation of  mega project  organised by Chattogram Nagorik Udduk in front of Chattogram Press Club  yesterday.

Indu Nandan Dutt, Member of Standing Committee of JASAD speaking at a human chain demanding implementation of mega project organised by Chattogram Nagorik Udduk in front of Chattogram Press Club yesterday.

Worker killed in fire

UNB, Chattogram :A worker died after a fire broke out at Four Season Sonali hotel in Foy's Lake area at Khulshi on Saturday morning. The deceased was identified as Khokon