Moheshkhali-Anowara parallel gas line ready for transmission from next month

  • Print
Chattogram Bureau :
The parallel  gas transmission line from Moheshkhali to Anowara is expected to resume transmission from June next as the 75 percent works of the project already completed in the meantime.
The under constructed transmission line at cost of Tk1157 cr  is expected to be completed by this time aimed at to supply the imported LNG (liquefied Natural Gas)  to national grid  from Moheshkali  terminal  under private management .
Gas Transmission company Ltd is implementing the project. Fuel experts opined that Bangladesh is going  one step ahead for fuel security in the country through installation of Moheshkahli transmission line. GTCL sources said another  79 kilometers long  pipe line  from Moheskhali to Anowara is being constructed by GTCL for supply of natural gas after refining the imported LNG . Four sister organizations including GTCL of Petro Bangla is  constructing this parallel gas transmission line at a cost of Tk1157 cr.
 Under the project  CTMS(custody Transfer Memory System)  installed at Anowara point It is learnt , under the first track projects o t the govt,  first pipe line project from Moheshkahli to Anowara was installed at a cost o f  Taka1,040 cr  in first phase. Through this pipeline, on average a day about 500 million cft natural gas is being supplied from Moheskhali terminal  after resification of the imported liquefied gas.
As a result, the consumers o f Karnaphuli Gas Distribution company are getting better advantages of fuel. Sources said after completion o f  first project , the second parallel line project from Moheshkali to Anowara under taken at a cost of Tk1157 cr  and after completion of  this parallet transmission line, all sorts complications in supplying   the resificated LNG gas to national grid will be removed without any suspicion. Project Director of Moheshkali Anowara parallel pipe line Project  Engineer Ariful Hoque Fakir told  media persons  that 75 percent works of the second phase project already completed and the  rest will be ended by end of June next . He   hoped that after completion of the project work, gas   transmission will be effected through both lines to avoid any complications in national grid .

More News For this Category

CCC Mayor A J M Nasir Uddin with other leaders of Chattogram City Awami League placing wreaths on the body of  A H M Harun recently.

CCC Mayor A J M Nasir Uddin with other leaders of Chattogram City Awami League placing wreaths on the body of A H M Harun recently.

.

Pass rate decreases, GPA-5 increases in Cox's Bazar

Cox'sBazar Correspondent :In  Cox's Bazar district, the results of the HSC examination has improved   compared to the previous year. The number of GPA-5 has increased this year . However, the

A MOU signing ceremony between Frobel Academy  and Daffodil Institute of IT( DIIT) , Chahttogram  was held in Port City recently.

A MOU signing ceremony between Frobel Academy and Daffodil Institute of IT( DIIT) , Chahttogram was held in Port City recently.

.

Traffic congestion in Chattogram, not for Port cause : Chairman

Chattogram   Bureau :Chairman  of Chatto gram  Port Authority Rear Admiral Zulfikar Aziz said the recent traffic congestion in port connecting road, Barik  Building to Fakirhat  and cement crossing in

MOU signing ceremony held

A Correspondent :Daffodil Institute of IT, Chattogram signed Memorandum of understanding with Frobel Academy to introduce my e-kids programme for the kids age level 4-17 years. MOU was signed

Mayor, CDA  Chief Visit Outer Ring Road in Port City

Mayor, CDA Chief Visit Outer Ring Road in Port City

Chattogram Bureau :Chattogram City Mayor AJM Nasir Uddin and  the Chairman of Chattogram Development Authority (CDA) Jahirul Alam Dobash visited the sites of outer Ring Road aimed at constructing

A discussion meeting was arranged by Bangabandhu Sanskritik Jote on the occasion of Confine Day of Sheikh Hasina on Monday .

A discussion meeting was arranged by Bangabandhu Sanskritik Jote on the occasion of Confine Day of Sheikh Hasina on Monday .

.

Students of different educational institutions at Chawkbazar area in the Port City  brought out a procession protesting eve-teasing and child violations recently. NN photo

Students of different educational institutions at Chawkbazar area in the Port City brought out a procession protesting eve-teasing and child violations recently. NN photo

.

3-day long Rag Day-19 begins at CUET

3-day long Rag Day-19 begins at CUET

Chattogram Bureau :A  3-day long  academic conclusion function titled CUET RAG-2019   began at Chattogram University of Engineering & Technology campus  from  Thursday (July 18)  . Dean of Architecture &

Rotary Governor visits Club of Ctg Rainbow

Rotary Governor visits Club of Ctg Rainbow

Chattogram Bureau :Governor of Ratary District-3282 Principal Lt.Col(Retd) M Ataur Rahman Peer visited  Rotary Club of Chittagong Rainbow on Wednesday .  Among others Chattered  President Rtn Jaheda Akhter Mita,